Centennial Hall in Wroclaw Vacation Packages
The initial works on the Centennial Hall (which involved construction site preparation) started in May 1911. In August and September, the principal construction axes were identified and earthwork commenced. By January 1912, the foundations were laid. In April, the work on scaffoldings and formworks for the Hall’s four main pillars started, and by September, the stage of covering the dome with concrete was successfully completed, and the formation of window frames and stepped tiers of walls and floors commenced. In December 1912, Dyckerhoff and Widmann presented the concrete shell to the City. It is a UNESCO World Heritage Site. Please note we do not offer hotels or other activities in this city at this time.
Tours to the Centennial Hall are available from Wroclaw.